China Sinks Giant Concrete Blocks to Build 119,000-Ton Wall Under the Sea

China Sinks Giant Concrete Blocks to Build 119,000-Ton Wall Under the Sea

google-g-white cross-white onedio-o-white
Onedio’yu Google’da tercih edilen kaynak olarak ekleyin plus-blue

The China State Construction Engineering Corporation (CSCEC) has achieved a historic milestone in a massive industrial park project in Qingdao city, Shandong province, that aims to bring together the maritime and energy sectors. In the offshore project, teams successfully placed the first colossal 3,500-ton cassette (concrete block) foundation designed for the southern breakwater on the seabed.

Scroll Down to Continue chevron-right-grey
Advertisement

The southern breakwater, which will reach a length of 675 meters upon completion, will be composed of a total of 34 massive pile structures operating on gravitational force.

The southern breakwater, which will reach a length of 675 meters upon completion, will be composed of a total of 34 massive pile structures operating on gravitational force.
english.cscec.com

When these blocks, each of which is approximately the size of a 5-story building and weighs 3,500 tons, are combined, it will be as if a colossal concrete wall weighing a total of 119,000 tons has been constructed under the sea.

Construction operations conducted far off the coast, in the open sea environment, are subject to challenging natural conditions.

Construction operations conducted far off the coast, in the open sea environment, are subject to challenging natural conditions.
english.cscec.com

Due to the constantly changing wind, waves, and currents, the construction team was compelled to operate within a very limited time frame.

A special installation plan was put into action to flawlessly place the giant cassettes into the sea:

A special installation plan was put into action to flawlessly place the giant cassettes into the sea:
en.clickpetroleoegas.com.br

The use of GPS technology ensured that the cassettes were positioned accurately, down to the centimeter.

To avoid any unexpected risks, tidal models were analyzed and flotation stability calculations were performed.

All ballast preparations, equipment checks, and emergency drills were completed without a hitch prior to the operation.

Once this colossal project, which pushes the boundaries of engineering, is completed, it will form the dock infrastructure of an integrated energy hub that combines offshore wind, solar, and hydrogen energy in a single center. The project also aims to significantly contribute to the overall infrastructure and logistic capacity of the region.

Scroll Down for Comments and Reactions chevron-right-grey
Advertisement

Keşfet ile ziyaret ettiğin tüm kategorileri tek akışta gör!

category/test-white Test
category/gundem-white Gündem
category/magazin-white Magazin
category/video-white Video
category/eglence REACT TO THIS CONTENT WITH EMOJI!
0
0
0
0
0
0
0
Scroll Down for Comments chevron-right-grey
Advertisement
WHAT ARE ONEDIO MEMBERS SAYING?
Send Comment